Project

General

Profile

Actions

Feature #253

open
NP NP

Canteen: D21 Dietary phase kickoff - chase ADR-0001/0002 sign-off

Feature #253: Canteen: D21 Dietary phase kickoff - chase ADR-0001/0002 sign-off

Added by Navya P. about 1 month ago. Updated about 1 month ago.

Status:
Resolved
Priority:
Normal
Assignee:
Target version:
-
Start date:
10/06/2026
Due date:
% Done:

100%

Estimated time:
Resolved By:

Description

Week 5, Day 21. Phase 3 (Dietary) is blocked on two unaccepted ADRs (0001: IPD owns diet order, Canteen owns fulfilment; 0002: diet-type master promoted to Admin). Neither IDietaryOrderReadContract nor Admin diet-type-master code exists yet. D21 tasks: 1) draft IDietaryOrderReadContract as a draft PR against integration/canteen-v1 on nuvita-shared-kernel; 2) draft the DietType entity plus IAdminServiceContract.GetDietTypesAsync as a draft PR against integration/canteen-v1 on nuvita-admin; 3) link both PRs on ADR-0001/0002 and request sign-off from IPD team, Admin team, and platform architecture. Checkpoint at end of day decides whether D22-D25 proceed as planned or fall back to contract-independent work. Plan: clinq-docs modules/canteen-management/plans/2026-10-05-canteen-v1-week-5-tdd-plan.md.

Actions

Also available in: PDF Atom